Encasement of inverted syphons

Projekt Informationen

Baumaßnahme

EVN western trunk gas pipelineAuersthal/
Ganserndorf – Langenschonbichl / Tulln

Ort

Auersthal, AT

Auftraggeber

EVN Netz GmbH Maria Enzersdorf

Bauausführung

ARGE Leyrer + Graf Bau GmbH – Nacap
Rohrleitungsbau GmbH

Bauzeit

April 2011 - June 2012

Projekt Details

Aufgabe

For the development of EVN Netz GmbH’s “West 4” western trunk gas pipeline between Auersthal / Gänserndorf and Langenschönbichl / Tulln, a consortium comprising Leyrer + Graf Bau GmbH and Nacap Rohrleitungsbau GmbH was contracted to build an approx. 60 km long pipeline section.

The route includes a series of inverted syphons by means of which the (DN 800) pipeline crosses under the many intervening waterbodies and watercourses. To protect the pipeline against mechanical damage and buoyancy or uplift, the inverted syphons were encased in concrete.

Lösung

The solution adopted to install the concrete encasement made use of HUESKER Synthetic GmbH’s Incomat textile formwork – in preference to the originally specified ballasting method by means of shuttered in-situ concrete. Incomat concrete mattresses comprise two high-strength woven layers connected by synthetic spacer ties. The mattress thickness is determined by the length of these spacers. The Incomat elements were filled with selfcompacting concrete (SCC) of class C 25/30 (minimum 28-day cylinder strength ≥ 30 N/mm2) to DIN 1045-2 (EN 206-1) so as to create a monolithic body of concrete within the textile formwork.

Vorteile

HUESKER Synthetic GmbH’s Incomat textile formwork helped to deliver a solidly built, easily installable, highperformance solution that fulfilled the necessary ballasting function for the inverted syphons.